The work to be carried out to create NET Line One's off-street stretch,
although more intensive, will be less disruptive than the work carried
out last year to modify the Robin Hood Line. There are very few times
when we need to take possession of the Robin Hood Line, and any that there
are will be on Sundays, so train services will be unaffected by the work.
Major works are needed on the David Lane level crossing, where the tram
tracks will be set into the road across the junction. Work around the
crossing will take place between the 3rd of June and the 12th of July.
Temporary closures of the crossing will be required for some of this time.
We will publicise details nearer the time.
At this stage there are no plans for any of the off-street works to be
carried out at night.
Laying tram tracks on Nottingham's streets began last year, with the
first complete stretch finished just before Christmas in Noel Street,
Hyson Green. We've now started in the city centre and track laying off-street,
alongside the Robin Hood Line and on the spur line from Highbury Vale
to Phoenix Park, begins at the end of February.

Location 1
Wilkinson Street to Basford
* Earthworks late February - mid April
* Drainage follows immediately
* Pole foundations early March
* Track laying early May
Note: Track laying on the depot site at Wilkinson Street is due to take
place from the end of February to mid May. Wilkinson Street will be one
of the access points to the worksite alongside the Robin Hood Line.
Location 2
Basford to Highbury Vale
* Earthworks mid March - late April
* Drainage early April to mid May
* Pole foundations late April
* Track laying late May - mid June
Note: Track will be laid across David Lane level crossing during June
and early July. The crossing will be closed to road traffic for some of
that time. More information will be available closer to the time. David
Lane will be one of the access points to the worksite alongside the Robin
Hood Line.
Location 3
Highbury Vale to Phoenix Park
* Earthworks mid March - mid April
* Drainage and ducts follows immediately
* Pole foundations late April/early May
* Track laying early June
Note: Rails, ballast and topsoil are to be stored in a temporary compound
on the Phoenix Park & Ride site.
Location 4
Highbury Vale to Bulwell
* Earthworks mid March - early June
* Pole foundations late April - mid May
* Drainage late May - mid June
* Track laying late July - early August
Note: Bulwell Station will be one of the access points to the worksite
alongside the Robin Hood Line.
Location 5
Bulwell to Hucknall
* Earthworks not needed in this location
* Drainage mid May - early July
* Pole foundations mid May - mid June
* Track laying all of August and September
Note: Track will be laid across Carey Road and Brickyard level crossings
late August/early September for two weeks. The crossings will be closed
to road traffic for some of that time. More information will be available
closer to the time.
Moor Bridge and Hucknall Station will be two of the access points to
the worksite alongside the Robin Hood Line.
|