The work to be carried out to create NET Line One's off-street stretch, although more intensive, will be less disruptive than the work carried out last year to modify the Robin Hood Line. There are very few times when we need to take possession of the Robin Hood Line, and any that there are will be on Sundays, so train services will be unaffected by the work.

Major works are needed on the David Lane level crossing, where the tram tracks will be set into the road across the junction. Work around the crossing will take place between the 3rd of June and the 12th of July. Temporary closures of the crossing will be required for some of this time. We will publicise details nearer the time.

At this stage there are no plans for any of the off-street works to be carried out at night.

Laying tram tracks on Nottingham's streets began last year, with the first complete stretch finished just before Christmas in Noel Street, Hyson Green. We've now started in the city centre and track laying off-street, alongside the Robin Hood Line and on the spur line from Highbury Vale to Phoenix Park, begins at the end of February.

Location 1
Wilkinson Street to Basford
* Earthworks late February - mid April
* Drainage follows immediately
* Pole foundations early March
* Track laying early May

Note: Track laying on the depot site at Wilkinson Street is due to take place from the end of February to mid May. Wilkinson Street will be one of the access points to the worksite alongside the Robin Hood Line.

Location 2
Basford to Highbury Vale
* Earthworks mid March - late April
* Drainage early April to mid May
* Pole foundations late April
* Track laying late May - mid June

Note: Track will be laid across David Lane level crossing during June and early July. The crossing will be closed to road traffic for some of that time. More information will be available closer to the time. David Lane will be one of the access points to the worksite alongside the Robin Hood Line.

Location 3
Highbury Vale to Phoenix Park

* Earthworks mid March - mid April
* Drainage and ducts follows immediately
* Pole foundations late April/early May
* Track laying early June

Note: Rails, ballast and topsoil are to be stored in a temporary compound on the Phoenix Park & Ride site.

Location 4
Highbury Vale to Bulwell

* Earthworks mid March - early June
* Pole foundations late April - mid May
* Drainage late May - mid June
* Track laying late July - early August

Note: Bulwell Station will be one of the access points to the worksite alongside the Robin Hood Line.

Location 5
Bulwell to Hucknall

* Earthworks not needed in this location
* Drainage mid May - early July
* Pole foundations mid May - mid June
* Track laying all of August and September

Note: Track will be laid across Carey Road and Brickyard level crossings late August/early September for two weeks. The crossings will be closed to road traffic for some of that time. More information will be available closer to the time.

Moor Bridge and Hucknall Station will be two of the access points to the worksite alongside the Robin Hood Line.

 

 

 

 

 